7.1.5 Restore to normal operation after “total off”

NOTE !

Make sure the UPS to be status of the activation of “total off”, i. e. Q1 closed, Q2 open
and the battery fuses F5, F6, F7
(and eventual external fuses in case of external
battery) connected.




View of the panel after pressing the button “total off”:

All Contactors are open.

Booster, inverter and Static-Switch shutdown.

LP 33 40kVA

APPLICAT. SUPPLY OFF

= 0%




1. Reset

total off”.

Restore the command “total off” by entering the screen:
MENU/RESET TOTAL OFF

LED TEST
RESET TOTAL OFF

*

The load is supplied by the mains through the automatic
bypass
.
The booster starts automatically.

The LCD screen must display the status:
APPLICATION ON BYPASS

LP 33 40kVA
APPLICATION ON BYPASS

= 70%

2. Switch ON the inverter by entering the screen:

MENU/COMMAND MENU/INVERTER ON

COMMAND MENU

INVERTER ON *
INVERTER OFF

The LCD screen must display the status:
APPLICATION ON UPS

LP 33 40kVA

APPLICATION ON UPS

= 70%

END OF PROCEDURE