GE Industrial Solutions LP 33 Series 30 & 40 kVA Operating Manual User Manual

Page 46

Advertising
background image

Modifications reserved

Page 46/57

OPM_LPS_3UO_30K_40K_0US_V010.doc

Operating Manual LP 33 Series 30 & 40 kVA

6. In order to discharge the DC link capacitors, start once more

the inverter on each unit through the screen:
MENU/COMMAND MENU/INVERTER ON

COMMAND MENU

INVERTER ON *

INVERTER OFF

Remark: command

INVERTER ON will be enabled only when

the inverter voltage of each phase decreases

below 7 VAC (about 30 seconds).

INVERTER: U1=

7V

U2= 7V U3= 7V
Frequency = 60.0Hz

Synchronized

Before proceeding to step 7, check on the display panel that
the DC link voltage (both polarities) Udcp and Udcn has reached

the minimum voltage of 5 VDC (about 30 seconds).

Udcp= 5V Udcn=

5V

Ubp=0V

Ubn=0V O

Charge level

= 0%

Autonomy =

0min

7. Switch OFF the inverter on each unit entering the screen:

MENU/COMMAND MENU/INVERTER OFF

COMMAND MENU

INVERTER ON

INVERTER OFF *

The load is now supplied directly from the mains through the manual switches Q2.

END OF PROCEDURE





WARNING !

The UPS cabinet contains parts electrically live.
Apart from the front door, do not open any other part of the UPS
.


NOTE !

With separate mains inputs, it’s possible to disconnect mains rectifier.