VENT INSTALLATION

INSTALLATION FOR VERTICAL TERMINATION

1. Determine the route your vertical venting will take. If ceiling joist,

roof rafters or other framing will obstruct the venting system,
consider an offset. See Figure 30 to avoid cutting load bearing
members.

For optimal flame appearance, a restrictor disk is necessary on straight
vertical runs of 20' of more.

• Runs may not incorporate elbows.

• The disk is part number 45D0551 and is included in installa-

tion manual packet.

• Drop the disk into a 4" inner collar before installing the first

section of flue or install at the last section before installing
the termination.

• An additional disk may be installed on runs of 35' or more.

Rotate disks perpendicular to each other.

NOTE: Pay special attention to these installation instructions
for required clearances (air space) to combustibles when
passing through ceilings, walls, roofs, enclosures, attic
rafters, etc. Do not pack air spaces with insulation. Also
note maximum vertical rise of the venting system and any
maximum horizontal offset limitations. Offsets must fall
within the parameters shows in Figure 13, page 20.

2. Set fireplace in desired location. Drop a line plumb down from

the ceiling to the position of the flue exit. Mark the center point
where the vent will penetrate the ceiling. Drill a small locating
hole a this point.

Drop a plumb line from the inside of the roof to the ceiling locat-
ing hole in the ceiling. Mark the center point where the vent will
penetrate the roof. Drill a small locating hole at this point.

FLAT CEILING INSTALLATION
1. Cut a 9

1

/

2

" (241mm) square hole in the ceiling using the locating

hole as a center point The opening should be framed to 9

1

/

2

"x9

1

/

2

"

(241mm x 241mm) inside dimensions as shown in Figure 32using
framing lumber the same size as the ceiling joist. If the area
above the ceiling is an insulated ceiling or a room, nail firestop
from the top side. This prevents loose insulation from falling into
the required clearance space. See Figure 31. Otherwise, install
firestop below the framed hole. See Figure 32.

2. Assemble the desired lengths of pipe and elbows necessary to

reach from the burner system flue up through the firestop. Be sure
pipe and elbow connections are fully twist-locked. See Figure
15, page 19.

Continued

Figure 30 - Offset with Wall Strap and 45°

Elbows

Roof

Flashing

Wall

Strap

45° Elbows

Ceiling Firstop

Figure 31 - If Area Above is a Room, Install

Firestop above Framed Hole as Shown

Figure 32 - If Area Above is Not a Room, Install

Firestop under Framed Hole as Shown

Firestop

Nails