4.1.4.1 Load shedding or sequential shutdown

It is possible to optimise backup time by shutting down non-priority equipment or sequencing the shutdown of
several devices.
Two shutdown criteria are possible:
Shutdown of outlets after a set battery back-up time (ShutOff Delay)
Shutdown of outlets at a given battery discharge level (ShutOff Level)
It is possible to specify values for both criteria. The first criterion reached will initiate server shutdown.

4.1.4.2 Sequential startup

It is possible to delay outlet power-on to reduce inrush currents on startup or to sequence the startup of several
devices.
Outlet startup after a given time is based on startup of the main outlet (Restart delay)