Suggested Specifications

©

2000–2003 Schneider Electric All Rights Reserved

142

09/2003

PART 3: EXECUTION

3.01 Inspection

a. Verify that the location is ready to receive work and the dimensions are as indicated.

b. Verify that power is available to the AC drives prior to installation.

3.02 Protection

a. Before and during the installation, the AC drive equipment shall be protected from site contaminants.

3.03 Installation

a. Installation shall be in compliance with manufacturer’s instructions, drawings and recommendations.

b. The AC drive manufacturer shall provide a factory-certified technical representative to supervise the

contractor's installation, testing, and start-up of the AC drive(s) furnished under this specification for
a maximum total of [ ] days. The start-up service shall be quoted as a separate line item.

3.04 Training

a. An on-site training course of [ ] training days shall be provided by a representative of the AC drive

manufacturer and quoted as a separate line item.