Installation and Removal

24

Figure 8. Adding the Grommet to the Power/Data Cable

13. On the media side of the printer, slide the split grommet onto

the power/data cable and insert it into the frame opening.
(Figure 8.)

14. Inspect the power/data cable to ensure approximately

17 inches of cable is exposed from the grommet to connect it to
the validator.

NOTE:

You will plug the power/data cable into the validator later.