R&M Materials Handling WIRE ROPE HOISTS Service User Manual

Page 109

Advertising
background image

R&M Materials Handling, Inc.
4501 Gateway Boulevard
Springfield, Ohio 45502
P.: (937) 328-5100
FAX: (937) 325-5319

109/130

R&M Materials Handling, Inc. reserves the right to alter or amend the above information without notice.

6.4 Double-girder

trolley

c_dab1a

1. Travel wheel
2. Rail


• Remove the temporary transport supports. Take the hoist out of the packing and move it to the

installation site. Lift the hoist using the lifting lugs provided.

• Check that the rail centers (B) on the main beam are suitable for the hoist trolley.

• Check that the groove (C) in the travel wheel is 15 mm wider than the rail width (A).

• Lift the hoist trolley onto the track.

• Check the proper installation and position of the runway end stops.
• Check that the hoist buffers are able to bump into the runway end stops or buffers of other trolley.

Note that in some hoist models the position of buffers can be changed.


6.4.1 Outfitting the hoist

• Install the power supply. Refer to the section “Connecting the to mains network”.

• Adjust the limit switch for hoisting. Refer to the section “Adjusting hoisting limit switch”.
• Carry out the commissioning inspection and complete the commissioning log. Refer to the section

“Commissioning”.


Advertising