Installation

CPS2500D Installation

Purpose

CPS 2500D Shelf Installation

Precautions

Observe ESD protection while installing circuit packs

Safety

• Always consider personal safety.

• Make sure the system is properly grounded per the National Electrical

Code and local building codes.

• Remove all metal jewelry before beginning the installation.

Installation Tools

• Wire cutters and strippers

• Heat shrink gun

• Torque wrench (0-240 inch-lb or 28 Nm)

• 5/16 inch (8mm) hex driver

• 10 mm hex driver

• 48 Volt test load

• Digital meter with an accuracy of +/- 0.02%

• Screw Drivers (flat-blade and Phillips)

• ESD wrist strap