Spectra and Spectra II Series™ Plug-In and Feeder Busway
Busway Installation Checklist

30

Outdoor and Dripproof Bus

17. Verify the orientation of weep holes. Are all open weep holes in joint caps,

elbows and shields facing downward?

Yes

(Do not remove shield plugs or weep-hole plugs in top or side positions.)

18. Are all drain holes clear in both bus and joint caps? (All construction debris removed.)

Yes

19. Were joints assembled within the width of the housing ground plates? (See outdoor step 4.)

Yes

20. Are 3/8" joint cap bolts properly tightened to 25 ft-lb (34 N-m), and all 5/16" joint cap

bolts tightened to 14-18 ft-lb (19-24 N-m)?

Yes

21. Were shields aligned at the edges of housing ground plates and all springs seated properly?

Yes

22. Were isolation joints screwed in place before end boxes (when present) were installed?

Yes

23. Were joint cap knockouts left in to set end boxes to 10 1/4 inches,

as shown in Figure 23 of DEH-40087?

Yes


Note: Please list any exceptions made to this checklist and any other comments related to the installation of this run of bus:

This checklist is intended to insure a sound installation of GE busway. It is not intended to cover all items related to the
installation, successful startup, and long-term use of the product and in no way relieves the contractor of his obligation to
meet all specification and code requirements.