2.2.

Inspection Procedures

The following inspection procedures should be performed immediately after your unit has arrived.
Report any damages immediately to your GE Service Team by calling (800) 637-1738. All freight
damage claims should be initiated with the freight carrier immediately.

1. C

ABINET

: Inspect packaging, exterior panels, and doors for any visible damage (i.e. scratches

dents, cracks, or torn packaging). If any damage is noted, please the GE Service Team at (800)
637-1738.

2. T

RANSFORMER

: Inspect the transformer for any loose connections or displacement during

shipment. Check to make sure all terminal lugs are tight and secure.

3. I

NTERNAL FEEDERS

: Ensure all lug connections are tight and secure.

Check the main input feeder connections at the main breaker to be sure vibration has not
loosened the terminal screws.

Using the same procedure, check the feeders from the load side of the main breaker to
the primary side of the transformer.

Check all other lugs (i.e. neutral bus, ground bus, terminal blocks, etc.).

4. O

UTPUT

D

ISTRIBUTION

C

ABLE

A

SSEMBLIES

: cable coils must be inspected for cuts and/or damaged

conduits. Each cable should be uncoiled and inspected individually.

Note: Do not remove the cable shipping pallet until the unit is near its final position

5. I

NPUT

P

OWER

J

UNCTION

B

OX

(P

OWER

J-B

OX

): carefully inspect the entire box for damage.