POWER WIRING INTRODUCTION + POWER WIRING (STANDARD CONTROL BOX)

WIRING

POWER WIRING INTRODUCTION

The standard control box can be wired for either 120 Vac or 240 Vac.

Factory default is 120 Vac. The Large Metal Control Box (XLM) can be

wired for 120 Vac (default) or it can be wired for 240 Vac with the

optional toroid transformer kit (refer to Accessories).
The batteries are charged in the circuit by the toroid transformer,

plug-in transformer, or the solar panels. Main power supply and control

wiring MUST be run in separate conduits.
Follow the directions according to your application. For solar

applications proceed to Solar Panels section on page 24.
NOTE:
If using an external receiver use shielded wire for the connections or mount

the receiver away from the operator to avoid interference with the operator.

AMERICAN WIRE

GAUGE (AWG)

MAXIMUM WIRE

LENGTH (120 VAC)

MAXIMUM WIRE

LENGTH (240 VAC)

14

130 feet

260 feet

12

205 feet

410 feet

10

325 feet

650 feet

8

520 feet

1040 feet

6

825 feet

1650 feet

4

1312 feet

2624 feet

POWER WIRING (STANDARD CONTROL BOX)

1

Turn off the AC power from the main power source circuit breaker.

2

Run the AC power wires to the control box.

3

Remove the toroid assembly from the control box by loosening the four screws

and lifting the assembly up and out.

4

Ensure the 120/240 plug is connected to either the 120 or 240 Vac connector on

the EMI board depending on your application. Factory default is 120 Vac.

5

Connect the ground wire to the ground screw on the back of the toroid assembly.

6

Connect the white wire from the toroid assembly to NEUTRAL using a wire nut.

7

Connect the black wire from the toroid assembly to HOT using a wire nut.

8

Replace the toroid assembly and tighten the four screws. Ensure the wires are not

pinched.

NOTE: Use copper conductors ONLY.

Toroid

Assembly

STANDARD CONTROL BOX

CONNECT BATTERIES

1

Plug the battery connector to the J15 plug labeled BATT(-)(+) DC(-)(+) on the

control board. The control board will power up. NOTE: You may see a small

spark when plugging the J15 plug into the board.

2

Turn ON AC power to the operator.

Battery Connector

J15 Plug

(back view of toroid assembly)

NEUTRAL

HOT

GROUND

White

Black

(incoming power wires)

240 Vac

Connector

120 Vac

Connector

Ground

Screw