15950-7

c. Panel software name and serial number

d. Type of controller: The network diagram shall depict the actual

connection sequence of the devices, including distances between

devices, type of wire used and serial number of controller.

2. The second drawing in the control package shall consist of actual installation

details, a valve schedule, and a damper schedule. The valve schedule shall

have entries for: Valve tag, system served, quantity type (3w, 2w), GPM,
actual CV, actual pressure drop, size, close off rating, spring range, part

number, and manufacturer. The damper schedule shall have entries for:

Damper tag, system served, quantity, type (PB, OB), CFM, size, actual

pressure drop, quantity of actuators, spring range, damper model number,

and, and actuator model number.

3. Subsequent drawings shall depict complete systems (air handler, chiller,

boiler, etc.). The drawing shall show the system schematic, all wiring of the

DDC controller, all wiring of field devices, starters, and connections to
equipment. Each drawing shall have a bill of materials and a sequence of

operation.

4. Floor plans shall depict equipment location, sensor, and panel locations. The

duct and space static pressure monitor points shall be shown.

D. Submittal data and control drawings for all equipment and systems shall be submitted (per

Section 01300) to the Architect/Engineer for review prior to ordering or fabrication of the

equipment. The following information shall be included in these submittals:

1. 30 Days or Less After Notice to Proceed:

a. Control valve and damper schedules which include size, Cv (valves), closeoff

pressure rating (valves), [at 0 psi for N.C., two-way valves; at 20 psi for N.O.,
two-way valves; and at 0 psi between ports A and B for three-way valves], gpm

or cfm, spring range of the actuator, quantity of actuators (dampers), and actual

pressure drop for each item.

b. Technical specification data sheets of each system component and device which

includes all data needed to show compliance with this specification.

2. 60 Days or Less After Notice to Proceed:

a. Control drawings with detailed piping and wiring diagrams; system schematics

with controlled/monitored device locations; and connections to all enclosures,
panels, and controllers, including a bill of material for all systems. Ladder-type

electrical schematic diagrams shall be provided for all interlock wiring with

magnetic starters, control relays, safety devices, etc.