b. Sequence of operation for all controlled and monitored points for each system.

Sequence shall be on same drawing as corresponding system schematic.

c. A complete input/output schedule for each DDC panel and dedicated controller

including point name (the same name to be used in software), functional

description of each point, point type, complete wiring diagram for each point

from controller to input or output device, field device type, and location, etc.

d. Communications cable schematic showing panel and controller locations, con-

troller power source, and all interconnecting data and communication conduc-

tors. Arrange the panels in the order in which they will actually be intercon-

nected in the field.

e. On control drawings show sensor, panel, and equipment locations by referring to

room number. VAV boxes shall be shown indicating room number that has

sensor or Smart Stat connected to controller. Also indicate, in a matrix-diagram,

each room served by that zone.

f. DDC network configuration complete with interconnection diagrams for all

peripheral devices, batteries, power supplies, etc.

g. A bill of material shall be shown on each drawing. The bill of material shall

include the device code used on the controls drawings, description of the

product, name of the manufacturer, complete model number, measurement range

(if applicable), and quantity.

h. Identify the electrical power source for each DDC panel by location (room

number), panel designation, and breaker number. Include the identification on

the drawing and at the DDC panel itself. (Dedicated Powersource)

i. Submittals shall also include a complete test plan and procedures. Test plan shall

be coordinated with the (Section 15990) Testing, Adjusting, and Balancing

Contractor. The test plan shall delineate the methods of testing and recording the

results of the point by point verification and calibration of the hardware and the

testing and tuning of the software. The test plan shall include a listing of all

hardware points with columns for calibration, test and certification. There shall

be a similar record for software.

3. 14- Days Prior to System Demonstration and Acceptance Testing:

a. Provide software programs and sequences written in the program language and in

English.

1.08 PROJECT RECORD DOCUMENTS

A. Upon completion of the installation, provide a complete set of record (as-built) drawings on

digital media. The content and format of the drawings shall be as described previously.