212

Seed Hawk™ Viper Pro™ Installation & Operation Manual

5.

Note the ‘Ttl Vol’ (total volume) column and the numbers for each node.

6.

Turn the section switches and the Master switch ‘On’.

7.

With a small jumper wire (or paper clip), short between the 2 o’clock and 6 o’clock sockets with a ‘short-no-
short’ motion. Each time contact is made, the Ttl Vol number should increase by increments of 1 or more.

8.

If the Ttl Vol total does not increase, remove the section of cable and repeat the test at the connector that is
the next closest to the node. Replace the defective cable as required.

9.

Verify the pin connection and voltage from the previous chart.

10.

If all of the cables test ‘good, replace the Flow Meter.

Note:

After testing is complete, re-enter the correct Meter Cal before starting application.