Activating the Endpoint

ORION Classic water endpoints are shipped in an inactive, non-transmitting state known as “Pause” mode . The endpoint offers

a Smart Activation feature . After the endpoint is installed, it begins broadcasting data when the encoder senses the first usage

of water . No field programming or special tools are required to activate the endpoint .

NOTE:

N

Endpoints shipped via air are shipped in “Stop” (hard sleep) mode and must be activated via IR communication using

an ORION handheld or mobile reading system and the ORION Endpoint Utility software .

RTR

When an RTR is mounted on the water meter, and the ORION endpoint connected to the RTR is securely installed, the ORION

system is ready for operation . The endpoint will turn on with water usage . Run water through the meter to increment the RTR

1/10th of the test circle . Upon receiving the first digital signal from the RTR, the endpoint counts the signal and begins its

radio frequency (RF) transmissions . No specific wire testing or endpoint programming is required .

NOTE:

N

Reading an ORION endpoint with the ORION handheld or mobile meter reading equipment immediately after

installation verifies proper operation and reading performance .

ADE, UNIV or ARB-V Endpoint

After the ORION endpoint is securely installed and the encoder is mounted on the water meter, the ORION system is ready

for operation . The endpoint will turn on with water usage . An ADE/UNIV/ARB-V endpoint requires up to one hourly reading

interval where consumption changes the electronic reading . For example, with an ORION endpoint connected to a six-dial

ADE, the encoder must detect consumption of 10 gallons before the endpoint will begin its RF data broadcast . Once it begins

broadcasting, the endpoint will update hourly based on the encoder odometer reading . No specific wire testing or endpoint

programming is required .

NOTE:

N

Reading an ORION endpoint with the ORION handheld or mobile meter reading equipment immediately after

installation verifies proper operation and reading performance .

Confirming an Installation

Before leaving the installation site, the installer can use an ORION handheld or mobile reading system to confirm the endpoint

wiring has been done correctly and that the endpoint is broadcasting RF data for reading . See the appropriate handheld or

mobile reading system user manuals for more information .