Integrated Pit Lid Hanger Installation Kit

ORION endpoints can be installed below composite and plastic lids that have an integrated hanger for AMR/AMI endpoints

using the Integrated Pit Lid Hanger Installation Kit (64394-009) .
To install an ORION endpoint to a composite or plastic lid with an integrated hanger, follow these steps and refer to

Figure 10

.

1 . Thread the lock nut onto the top of the ORION endpoint as shown .
2 . Slide the endpoint into the lid bracket .
3 . Tighten the lock nut so that the endpoint is held firmly in place .

Figure 10: Integrated pit lid hanger installation

VAULT INSTALLATION

For a deep vault installation, Badger Meter offers a Vault Installation Kit (64394-008) that can be used to mount the

endpoint to the side of the vault .
To install an ORION endpoint in a deep vault, follow these steps and refer to

Figure 11

.

1 . Mount the C-clamp on the side of the vault . Select a location inside the vault, close to the top, that will not be

damaged when access to the meter is required .

2 . Place the neoprene spacer supplied in the installation kit around the endpoint, approximately 1/2 inch from the top

of the endpoint .

3 . Thread the lock nut on the endpoint until it makes contact with the neoprene spacer as shown in

Figure 11

.

4 . Insert the endpoint into the C-clamp as shown .
5 . Close the C-clamp and lock it in place so that it closes over the neoprene spacer and securely holds the endpoint .

NOTE:

N

ORION radio endpoints perform best with a clear line of sight . Performance varies by installation and

lid construction .

C-Clamp

C-Clamp around endpoint

Figure 11: C-Clamp and placement

Lid bracket

Lid bracket

Meter pit lid

ORION endpoint

Lock nut