Before connecting the thermostat, check to make sure the

wires will be long enough for servicing at a later date. Make

sure that thermostat wire is long enough to facilitate future

removal of blower for service.

Complete the wiring connections to the equipment. Use the

provided unit wiring diagram and the field wiring diagram

shown in Figure 33. Use 18 gauge wire or larger that is

suitable for Class II rating for thermostat connections.

Electrically ground the unit according to local codes or, in

the absence of local codes, according to the current National

Electric Code (ANSI/NFPA No. 70). A green ground wire is

provided in the field make-up box.

NOTE: This furnace contains electronic components that

are polarity sensitive. Make sure that the furnace is wired

correctly and is properly grounded.

Accessory Terminals

One line voltage “EAC” 1/4" spade terminal is provided on

the furnace integrated control. See figure 34 for integrated

control configuration. This terminal is energized when the

indoor blower is operating. Any accessory rated up to one

amp can be connected to this terminal with the neutral leg

of the circuit being connected to one of the provided neutral

terminals. If an accessory rated at greater than one amp is

connected to this terminal, it is necessary to use an external

relay.

One line voltage “HUM” 1/4" spade terminal is provided on

the furnace integrated control. See Figure 34 for integrated

control configuration. This terminal is energized in the

heating mode when the combustion air inducer is operating.

Any humidifier rated up to one amp can be connected to

this terminal with the neutral leg of the circuit being connected

to one of the provided neutral terminals. If a humidifier rated

at greater than one amp is connected to this terminal, it is

necessary to use an external relay relay.

Generator Use - Voltage Requirements

The following requirements must be kept in mind when

specifying a generator for use with this equipment:

The furnace requires 120 volts ± 10% (Range: 108 volts

to 132 volts).

The furnace operates at 60 Hz ± 5% (Range: 57 Hz to

63 Hz).

The furnace integrated control requires both polarity and

proper ground. Both polarity and proper grounding

should be checked before attempting to operate the

furnace on either permanent or temporary power.

Generator should have a wave form distortion of less

than 5% RHO.

Thermostat

Install the room thermostat according to the instructions

provided with the thermostat. See Figure 31 for thermostat

designations. If the furnace is being matched with a heat

pump, refer to the FM21 installation instruction or appropriate

dual fuel thermostat instructions.

Indoor Blower Speeds

1. When the thermostat is set to “FAN ON,” the indoor

blower will run continuously on the heating speed when

there is no cooling or heating demand.

2. When the unit is running in the heating mode, the indoor

blower will run on the heating speed.

3. When there is a cooling demand, the indoor blower will

run on the cooling speed.

Condensing Unit Thermostat Designations

(Refer to Specific Thermostat and Outdoor Unit.)

* Note: “R” Required on some outdoor units.

Figure 31

Advertising
This manual is related to the following products: