SERVICE (Cont.)

WHI/BLU to

Relay N.O.(K4)

WHI to Cordset (120V)

RED/BLK to Cordset (230V)

GRN to Ground (120V)

GRN/YEL to Ground (230V)

P1310

FIG. 4 AC MOTOR TERMINALS

11. Clean all grinding burrs and mounting surfaces

before reassembly.

12. Install the four .250”-20 cage nuts on the new

motor.

13. Place the new motor with hopper collar and bush-

ing into position on the bushings on the motor

mounting bracket.

14. Using four .250”-20 screws, flat washers and

rubber washers secure the motor to the mounting

bracket.

15. Install stationary burr (9) to the grind chamber

housing using two .250”-20 screws.

16. Install burr (7) and burr auger rotor/spring as-

sembly (3) on to motor shaft.

17. Install motor shaft extension (11) on motor

shaft.

18. Align the slot in the motor shaft extension (11) with

the slot in the burr auger rotor/spring assembly

(6) and install shear plate (4).

AC MOTOR AND GRIND CHAMBER (cont.)

19. Install burr rotor cup (5).

20. Install grind selector dial plate and grind selector

knob assembly on the grind chamber housing and

secure with two .250”-20 screws.

21. Refer to Fig. 4 and reconnect the wires.

22. Refer to ADJUSTMENTS in the Installation and

Operating Manual, and reset the burrs.