scReW alIGnMenT (conTInUeD)

The template panel should be laid out for the proper screw locations in accordance with the
building erection drawings . Since pre-drilling will “hand” the panels, it will also be necessary to
select the end of the building from which the paneling is to begin . Before drilling the template
panel, it should be checked for proper hole locations against the building framework . Be sure there
is no excessive deflection in the purlins and girts .

2"

1

1

/

4

˝

3

/

4

˝

1

1

/

2

˝

1˝ - 1

1

/

2

˝

12˝ Lap

Dimensions subject to

variations. Check building

erection drawings.