Roof sheeting sequence – Mueller Pre-Fab User Manual

Page 61

Advertising
background image

www.muellerinc.com

E-15

Roof sHeeTInG seQUence

It is recommended that both sides of the ridge of a building be sheeted simultaneously . This will
keep the insulation covered for the maximum amount of time and the panel ribs can be kept in
proper alignment for the ridge panel . Check for proper coverage as the sheeting progresses .

note

panel-sheeting sequence below.

5

6

7

8

9

10

11

12

1

2

3

4

noTe: If slippery substances are present on the roof panels wipe them clean

immediately to prevent slipping or falling. Workers should maintain a constant

awareness of their location relative to the roof edge.