SECTION 3 - CHASSIS & TURNTABLE

3121202

– JLG Lift –

3-39

BEWARE OF SHARP EDGES OF THE COUNTERBORE WHILE SEAT-
ING THIS O-RING.

12. THe cover (6) is now installed on this assembly. Tak-

ing care to correctly align pipe plug hole (20) with
those in the hub (1J), usually 90° to one another.
Locate the 4 counterbore holes in hub (1G) (marked
in step 3) and install 4 shoulder bolts (13). A slight
tap with a hammer may be necessary to align shoul-
der bolt with hub (1G) counterbore.

13. Install regular grade 8 bolts (12) into remaining

holes.

14. Pipe plugs (20) are to be installed into cover (6)

using a lubricant of some sort.

15. Torque shoulder bolts (13) to 23-27 ft./lbs. and regu-

lar grade 8 bolts (12) to 23-27 ft./lbs,

This completes the assembly. THe unit must be filled one-
half full of EP 90 lubricant before operation if the unit is
mounted horizontally, and completely filled if mounted
vertically. In vertical mounting application case oil circula-
tion is recommended.