THE TOOLS REQUIRED FOR INSTALLATION


Listed below are some of the tools needed to install the FREIGHTLIFT in a professional
and prompt manner. Individual site situations and a basic variation in the types of units
may dictate the need for additional items.

Welding Machine and Equipment

Hack Saw, Sawzall, or

Cutting Torch with Full Tanks

Portable Band Saw

Fire Extinguisher

Drill and Drill Bits

Forklift Extension

Cords

Chain Fall

Sledge Hammer

Come-A-Long

Open or box end wrench

Cables or Hook Chains with 1,000# Cap.

Drift Punch

Disk Grinder

Carpenter’s Square

“C” Clamps (12” opening)

Chalk Line

Socket Set (1/2” drive, sockets to 1 1/8”)

Plumb Bobs

Pinch Bar

4’ Level

Hammer Drill & Bits for 1/4”, 3/8” and

25’ / 100’ Measuring Tape

1/2” anchors

Broom

The following supplies will also be needed:

*Concrete anchors (16 minimum) sized for the required minimum pullout of the base
floor channels and upper level bracing. Refer to the approval drawing since the size of
the anchors can vary for each installation.

*Concrete anchors for accessories, such as enclosures, approach ramps, etc. (Usually
1/4” diameter anchors and at least 12 anchors, minimum.)

*Shim stock for the mast beams, platform carriage corners, and/or approach ramp (if a
part of this installation)

*Paint (Autoquip Blue: available in 1 and 5 gallons, as well as spray cans)

*3” x 3” steel angle iron or 4” channel for additional bracing

ALSO - BEFORE YOU BEGIN :

1. Beams are too heavy to lift manually and require lifting equipment. Check for

availability of overhead attachment of chain fall or of fork truck before you start.

2. Before you will be able to complete the installation the unit must be operated,

therefore power to the motor is required. Arrange for power before starting
installation.