NOTE: All illustrations contained in this manual are for reference purposes only.
Specific applications and site conditions may require different anchoring and bracing
procedures. The ultimate responsibility for the anchoring and bracing rests with the
installation crew.

A. LAYING OUT CARRIAGE POSITION & MARKING FLOORS FOR ALLIGNMENT

1. Refer to Figures 11-15 to lay out and mark the reference lines so that the lift will

clear the upper landing and any obstructions that may be located around the lift (the
General Arrangement Record Drawings should indicate the necessary clearance
needed for the particular application).

a. Figure 11 - Layout the position of the lift at the second level landing/opening,

marking the center of the carriage first – then both outside edges of the carriage.


b. Figures 12 & 13 - Drop a plumb line from the center marking of the carriage

position at the second floor holding the plumb line one inch out from the edge of
the landing (one inch is a standard distance for clearance - deviations may
occur), or point A, down to the first floor and mark point B as the carriage center
(check the GA drawing for any other special considerations).

NOTE: To ensure carriage clearance between floors, remove any protrusions
from the floor, wall, etc., or move the plumb lines out beyond the protrusions.


c. Figure 14 - Drop plumb lines from the upper level to the lower level using the

two markings identifying the outside edges of the carriage platform. Again, the
plumb line must be held 1” out from the edge of the mezzanine or opening at the
second floor to provide adequate clearance.

d. Figure 15 - Using a chalk line, snap a line between C and D.

NOTE
: The carriage will be aligned to this point. Also, always check the pit
and floor openings for correct dimensions and squareness
.