Includes offset and center-set glazing), Fig. 62, Fig. 63 – EFCO 433 Series User Manual

Page 71

Advertising
background image

June 2012

PART NO. Y017

Page 71 of 90

Series 433 Triple Set Installation Instructions

SECTION VIII: Installation

(Includes Offset and Center-Set Glazing)























Step 9) Snapping the Expansion Mullion (Center-Set Mullion)

To snap the expansion mullion together, line up the mullion halves and gaskets. See
Figure 62. Place one clamp at the bottom of the expansion mullion using wood blocks

to protect the extrusions. Tighten the C-clamp until the expansion mullion halves begin
to snap together. Place another set of wood blocks and a C-clamp at the middle of the

expansion mullion and tighten it. Then repeat the same process on the top. Tighten
the C-clamps until the sight line becomes 2". It may be necessary to work from one

clamp to the next several times, or move the clamps, to ensure the mullions are
snapped together evenly. See Figure 63. DO NOT try to hammer the expansion
mullion together! This will dent, bend, scratch, or deform the expansion mullion and

may cause it to leak. Anchor the head using the requirements shown on page 64
before installing the next ladder. If this is the last ladder, anchor the jambs as required

on page 65 and proceed to the perimeter sealing process, Step 11 on page 72.

[FIG. 62]

8397

8396

2.000"

8396

8397

WOOD BLOCK

C-CLAMP
OR SIMILAR

[FIG. 63]