Installation, Receiving inspection, Safety checklist – B&C Technologies PF Series User Manual

Page 14: Chapter 5 installation, 1 receiving inspection, 2 safety checklist

Advertising
background image

Chapter 5

Installation

5.1

Receiving Inspection

Upon receipt of the equipment, visually inspect for shipping damage and note any damage with
the carrier before signing the shipping receipt, or advise the carrier of the damage as soon as it is
noted.

If damage is discovered, a written claim must be filed with the carrier as soon as possible.

Note: Warranty is VOID unless the equipment is installed according to instructions. The installa-
tion must comply with the minimum requirements listed in this manual. All national, state and
local codes must be followed including but not limited to gas, electrical, plumbing and HVAC.
Due to various requirements, statutory codes should be well understood before installation com-
mences.

Important: The machine should be transported and handled in an upright position.

5.2

Safety Checklist

Before Initial start up of a B&C folder perform the following safety check:

1. Make sure all electrical and pneumatic connections have been made in accordance with ap-

plicable codes and regulations.

2. Make sure the machine is grounded electrically.

Before machine is placed in operation, the safety interlocks must be checked for proper operation
as follows:

1. When the machine is energized electrically and in operation, the electrical panels and safety

guards must be locked in the closed position. Verify this by attempting to open the panels

10

Advertising