3. Installation

3-1

3.1 Transportation


When loading and unloading unit, be sure to use the lifting bail provided on the center of the unit top.

Never get under the unit which is lifted up, because it is very dangerous.

When unit is transferred or moved from working site, be sure to place it on truck bed, and fasten it by

ropes.

Never lift unit which is still in operation, or it could cause critical damage to each component or lead to

serious accident.

When lifting unit up, make sure that all the fixing bolts on the bonnet are surely tightened because it is

feared that the unit may fall.

3.1.1 Lifting up

Before lifting the unit up, make sure to check

the lifting bail for any crack and loosened
bolts.

Connect the hook“1”of the crane or shackle

with lifting bail“2”eye fitted at the top center
of the unit, and make sure that there is no
person standing around the unit. Then
perform hoisting operation.

Select a truck or a crane with capacity

sufficient for weight and size of the unit by
referring to the values shown in Chapter 8
“Specifications“ of the manual.

3.1.2 Movement with a forklift

Protect the package from damage with

cushion material“3”

Make sure to insert the fork“4”more

than half of the length of the unit for

security.





3.1.3 Mounting the unit on the truck bed

Be sure to put chocks“5”at the front and rear

frames to the machine.

Hook the rope“6”as shown in the figure. Thus

secure the unit on the truck bed.