8unitary products group – Thermo Pride Air Handler MA User Manual

Page 8

Advertising
background image

8

Unitary Products Group

SECTION VII: LINE POWER

CONNECTIONS

Power may be brought into the unit through the supply air end of the

unit (top when unit is vertical) or the left side panel. Use the hole appro-

priate to the unit’s orientation in each installation to bring conduit from

the disconnect. The power lead conduit should be terminated at the

electrical control box. To minimize air leakage, seal the wiring entry

point at the outside of the unit. See Figure 3.

Refer to Tables to determine proper wire sizing:
Tables 8 & 9 for cooling only or,

Tables 12 & 13 for single phase or,

Tables 15 & 16 for three phase or,

Table 18 for 460V.

SECTION VIII: BLOWER SPEED

CONNECTIONS

All air handlers contain 3-speed blower motors which are prewired to

the control board.

Adjust blower motor speed to provide airflow within the minimum and

maximum limits approved for evaporator coil, electric heat and outdoor

unit. Speed tap adjustments are made at the motor terminal block, See

Figure 8 or 9. Airflow data is shown in Tables 19 & 20.
Connect motor wires to motor speed tap receptacle for speed desired.

See wiring label for motor wiring details.

FIGURE 7: Line Power Connections

ELECTRIC HEAT

WITHOUT CIRCUIT BREAKER

SINGLE SOURCE (2.5 - 10 KW)

GND. LUG

POWER
SUPPLY

GND.
LUG

ELECTRIC HEAT

WITHOUT CIRCUIT BREAKER

3 PHASE (10 - 15 KW)

GND. LUG

POWER
SUPPLY

GND.
LUG

1 PHASE ELECTRIC HEAT

WITH CIRCUIT BREAKER

AS SHIPPED FROM FACTORY

SINGLE SOURCE

(2.5 - 25 KW) - 25 KW SHOWN

GND. LUG

POWER
SUPPLY

GND.
LUG

1 PHASE ELECTRIC HEAT

WITH CIRCUIT BREAKER

& BREAKER BAR REMOVED

MULTI-SOURCE (15 - 25 KW) - 25 KW SHOWN

GND. LUG

POWER
SUPPLY 1

GND.
LUG

POWER
SUPPLY 2

POWER
SUPPLY 3

TYPICAL WIRING WITHOUT ELECTRIC HEAT

GND. LUG

POWER
SUPPLY

GND.
LUG

POWER WIRING (208/230-1-60)

NOTE: USE ONLY COPPER CONDUCTORS

TERMINAL
BLOCK

TERMINAL
BLOCK

MAY BE 1, 2, OR 3
CIRCUIT BREAKERS

MAY BE 1, 2, OR 3
CIRCUIT BREAKERS

(JUMPER BAR)

CONNECT LEADS WITH WIRE NUTS
(TYPICAL ALL HEAT KITS)

FIGURE 8: 460V - Line Power Connections

ELECTRIC HEAT

WITHOUT CIRCUIT BREAKER

3 PHASE (10 - 15 KW)

GND. LUG

POWER
SUPPLY

GND.
LUG

3 PHASE ELECTRIC HEAT

WITH CIRCUIT BREAKER
MULTI-SOURCE - 25 KW

GND. LUG

POWER
SUPPLY 1

GND.
LUG

POWER
SUPPLY 2

TERMINAL
BLOCK

CONNECT TRANSFORMER LEADS WITH WIRE NUTS
(TYPICAL ALL HEAT KITS)

(2) 3-PHASE

BREAKERS

FIGURE 9: Blower Speed Connections

FIGURE 10: 460V - Blower Speed Connections

FACTORY WIRED TO
TRANSFORMER

FACTORY WIRED TO
FAN MOTOR RELAY
TERMINAL ON
CONTROL BOARD

YEL

PUR

PUR

HIGH

MED

LOW

GND.

230 VOLT
BLOWER MOTOR

CAP

BRN

ORG TAPE END & CAP

WITH WIRE NUT

L1

460 VOLT
BLOWER
MOTOR

L2

HIGH

HIGH

MED

LOW

PUR

BRN

460 VOLT BLOWER MOTOR

ORG

L1

460 VOLT
BLOWER
MOTOR

L2

MEDIUM

HIGH

MED

LOW

PUR

BRN

ORG

460 VOLT
BLOWER
MOTOR

L2

LOW

HIGH

MED

LOW

PUR

BRN

L1