3 refrigerant piping, Refrigerant piping, Table 5 – Emerson 3000 User Manual

Page 31: Recommended line sizes — od copper (inches), Notice

Advertising
background image

Air-Cooled Models—Self-Contained Compressor

25

3.3

Refrigerant Piping

All refrigeration piping should be installed with high temperature brazed joints. Prevailing good

refrigeration practices should be employed for piping supports, leak testing, dehydration and charg-

ing of the refrigeration circuits.
Unit refrigeration components and piping are shipped from the factory with a nitrogen holding

charge.

NOTICE

Risk of improper installation. Can cause equipment and property damage.
The refrigeration piping should be isolated from the building by the use of vibration isolating

supports.
When installing field piping, care must be taken to protect all refrigerant lines from the

atmosphere, especially when using refrigerants with POE oils. Do not allow the piping to

stand open to air for more than 15 minutes. Units designed for R407C have a compressor that

contains POE oil that is very hygroscopic; that is, it quickly absorbs water from the air. The

longer the compressor piping is left open to air, the harder it will be to fully evacuate. If left

open too long, the POE oil may need to be replaced before achieving the required vacuum

level.
Keep the evaporator unit and condenser closed with their factory charge of dry nitrogen while

all field piping is installed. Keep the field piping clean and dry during installation, and do not

allow it to stand open to the atmosphere. When all the field interconnecting piping is in place,

vent the condenser dry nitrogen charge and connect to the field piping. Finally, vent the

evaporator unit dry nitrogen charge and make its piping connections last.
Follow all proper brazing practices including a dry nitrogen purge to maintain system

cleanliness.

Traps should be installed in the hot gas line on vertical risers at the base and every 25 feet (7.6

meters) in elevation. These traps will collect condensed refrigerant and refrigerant oil during the off

cycle of the unit and ensure flow of refrigerant oil during operation.
A check valve is factory-supplied with the unit to be field-installed on the discharge side of the scroll

compressor. Be sure to install the check valve with the refrigerant flow in the proper direction. When

soldering or brazing the valve, it is very important to protect the internal parts by wrapping the valve

with a damp cloth to keep the valve temperature below 250°F (121°C).
Approval is required whenever:

• a refrigerant piping run exceeds 150 ft. (46 m) equivalent length
• an R407C system condenser must be located below the level of the cooling coil.

Total discharge line pressure drop must not exceed 10 PSIG (69 kPa).
Consult your local Liebert representative when considering installations outside these guidelines.

NOTE
Piping, including inverted trap(s), must be routed to allow unobstructed access to the panel

per the NEC.

Table 5

Recommended line sizes — OD copper (inches)*

Equivalent Length

3.5-ton 042A (040A)

5-ton 067A (065A)

Hot Gas Line

Liquid Line

Hot Gas Line

Liquid Line

50 ft. (15 m)

5/8

1/2

7/8

1/2

100 ft. (30 m)

3/4

1/2

7/8

5/8

150 ft. (45 m)

3/4

5/8

7/8

5/8

*Recommended vertical line sizes must be used for proper oil return at all cooling and dehumidification steps.

Advertising