Installing DC Power Supplies

Figure 16 E1200i DC PEM Front Panel

Cable and Connector Requirements

You must provide your own cables to connect to a remote power source (for example, a circuit breaker
panel) in your equipment rack or office. Cables must be sized to meet the following criteria:

rated for at least 150A service to allow for a fully loaded E1200i DC system at low input voltage per
your local electrical codes

limits voltage drop across the cable length to 0.5V or less

Before you make the cable connections, apply a coat of antioxidant paste to un-plated metal contact
surfaces. File un-plated connectors, braided straps, and bus bars to a shiny finish. It is not necessary to file
and coat tinned connectors or other plated connection surfaces, such as on the E1200i DC PEM studs.

Installing DC PEMs

Each E1200i DC system requires at least one load-sharing DC PEM to operate. Two units are
recommended for full facility redundancy.

Parameter

Specifications

Maximum DC PEM Input Current

150A

Maximum Power Dissipation

6850W (21,598 BTU/hour)

Input Voltage

-48 to -60 Vdc

CC-E1200-PWR-DC

-48/-60Vdc
150A, 7200VA

Status

Latch Release

PEM interlock

lever

Over-current protector

Locking screws

Studs

FN00102lp