SPX Cooling Technologies Evaporative Air Cooler FSIG-TS-08A User Manual

Page 14

Advertising
background image

Specifications

Specification Value

Marley

/

Sigma F Series

Cooling Tower

/

Specifications: Base

14

3.0

Construction:

3.1

The tower shall be capable of with-

standing water having a pH of 6.5 to

8.0; a chloride content (NaCl) up to 750

ppm; a sulfate content (SO4 ) up to

1200 ppm; a calcium content (CaCO3)

up to 800 ppm; silica (SiO2) up to 150

ppm; and design hot water tempera-

tures up to 120°F (48.9°C). The circulat-

ing water will contain no oil, grease,

fatty acids, or organic solvents.

3.2

The structural framework of the tower
shall be pultruded or molded fiberglass,
designed in accordance with ASCE
Structural Plastics Design Manual. All
allowable design values shall be factored
for wet service, temperature, and duration
in accordance with standard engineering
practices.

3.3

Basic design criteria shall be 30 psf

(1.44 kPa) wind load and 5%g seismic

load.

3.4

Multicell towers shall include stainless

steel partitions between cells in the fill

areas, and fiberglass partitions in the

plenum area. Partitions shall extend

the full height of the tower from the

base of fill to the underneath side of

the fan deck.

3.5

Column lines shall be on no greater

than 4'-0" (1.22 m) longitudinal centers,

and the base of all columns shall be

firmly anchored to series 304 stainless

steel base plates. Framing joints shall

be made with 1/2" diameter or larger

series 300 stainless steel machine

bolts. Critical framing joints shall be

augmented with 1.06" OD heavy wall

fiberglass sleeves to transmit loads.

3.6

No field gluing of joints, or any other

structural member, will be allowed.

The limiting water quality values indicated are those which are

acceptable for the normal materials of construction specified. If

water of more aggressive quality is anticipated please change

hardware material requirement to series 316 stainless steel, or

silicon bronze, as you may have agreed upon beforehand with

the Marley sales representative.

If there is any doubt in your mind as to the grade of hardware

that is appropriate to your water quality, please have a sample of

it analyzed and provide Marley with a copy of the analysis.

Discuss higher design loadings with your Marley sales represen-

tative.

Multicell towers must have plenum partitions between cells.

Otherwise, air will be induced downward through an inoperative

fan, bypassing the fill entirely. Without these partitions, part-load

or off-season operation of the tower would be completely unsat-

isfactory.

Fill partitions prevent the random migration of water from cell to

cell, and permit individual cell operation during reduced ambient

or low load conditions.

The variable weather conditions encountered during on-site

construction of cooling towers does not result in the stable condi-

tions of temperature and humidity that assure proper bonding

during the gluing process.

Advertising