Section 300-Installation

Chapter 3. Cabinet Installation

DBS-2.3/9.2-300

DBS Manual - Revised April 2000

3-17

System Initialization

1. Confirm that the DBS power switch is OFF.

2. Plug the power cord into a dedicated 120V 15 amp AC wall outlet.

Note: A surge protector should be installed on the power cord.

3. Set SW1 on the CPC card to RAMCLR (RAM Clear).

Figure 3-17. CPC memory clear switch

4. Turn the power switch on.

As the system loads, the bottom LED lamp on the CPC card will flash.

5. Once the bottom LED lamp on the CPC card stops flashing, set SW1 on

the CPC to RAMHOLD.

R A M H O LD

TRK1

TRK2

TRK3

EC1

EC2

EC3

EC4

EC5

EC6

EC7

EC8 EC/TRK SCC

CPC

AUX1

AUX2

STATU S
LED

SW 1

R A M C LR