Rack power and grounding

To ensure a complete power and grounding installation:

In rackmount server installations, ensure the CallPilot server chassis
and equipment racks are isolated from other foreign sources of ground.
Acceptable isolation methods include: isolation pads, grommeted
washers, chassis side rail strips, and non-conducting washers.

In rackmount server installations where other equipment is also installed
in the same 19" rack, ensure that all equipment derives ground from

Nortel CallPilot

1002rp Server Hardware Installation