Opening a ceiling and installation of hanging bolts

<Treatment of ceiling>

The ceiling differs according to structure of building. For details, consult your constructor or interior finish contractor.

In the process after the ceiling board has been removed, it is important to reinforce ceiling foundation (frame) and to
keep horizontal level of installed ceiling correctly in order to prevent vibration of ceiling board.

(1) Cut and remove the ceiling foundation.

(2) Reinforce the cut surface of ceiling foundation, and add ceiling foundation for fixing the end of ceiling board.

<Installation of hanging bolt>

Use M10 hanging bolts (4 pcs, to be local procure). Matching to the existing structure, set pitch according to size in
the unit external view as shown below.

Installation of ceiling opening and hanging bolt

Adjust nut position (lower side) so that clearance between the
attached washer (lower side) and ceiling board is 88mm.

Anchor bolt

(Blade type

bracket)

(Slide type

bracket)

(Pipe hanging

anchor bolt)

Rubber

Hanging bolt

Hanging bolt

Support angle

Hanging bolt

Washer
(Upper side)

(Hanging bracket
main unit)

Washer
(Lower side)

Nuts (Lower side)

Nut (Upper side)

Ceiling boards

88mm

Hanging bolt

Hanging bracket

Level

Indoor unit

Level vial (Horizontal: within 5mm)

Hanging bolt

Hanging
metal

Installation

gauge

Ceiling board

1) 20 to 30

mm

2) 12 to 17

mm

Hanging bolt
(W3/8 or M10)

Nut
(W3/8 or M10)

(1) Required those other than M10 flat washer at site.

(2) To prevent falling-off of bolt (safety), be sure to

set it just under the hanging bracket as shown
in the figure.

(1)
M10 flat washer
(Accessory)

(2)
M10 flat washer
(Accessory)

Nut
(W3/8 or M10)

Installation
gauge

2) 20 to

30mm

1) 12

mm

+5

–0

Ceiling
board

Indoor unit

• Hang up the main unit by hanging the nut of hanging bolt to

T groove of hanging bracket of the main unit.

• Using the level vial, etc., set the horizontal level of the main

unit within 5mm.

• Using the installation gauge, check and adjust the positional

relation between the main unit and ceiling opening hole, and
hanging-up height of the main unit. (Direction to be used is
indicated on the installation gauge.)

1) Check lower side of the indoor unit locates at position (12

to 17) mm higher than the lower surface of the ceiling
board. (4 corners)

2) Check clearance between side of the indoor unit and the

ceiling board is 20 to 30mm. (Common to 4 corners)

New concrete slab

Install the bolts with insert brackets or anchor
bolts.

Steel flame structure

Use existing angles or install new
support angles.

Existing concrete slab

Use a hole-in anchors, hole-in
plugs, or a hole-in bolts.