37.

Using the two

5

16

”-24 nuts

supplied, tighten the studs into

the intake by threading both nuts

onto the stud, then tighten the nuts

against each other with two

1

2

” open

end wrenches. Tighten and torque

the stud to 2 ft-lbs by turning the top

nut. Remove the nuts from the stud

by using two open-end wrenches to

loosen the nuts in relation to each

other. Repeat the process for each

stud. The process

is shown in Figure 15.

38.

If your vehicle is NOT equipped

with a factory ground strap on the

intake heater, install the supplied

ground strap from the intake heater

to the engine. Put a 6-mm washer

onto the bottom intake heater

stud, leaving the factory heater nut

installed. next, install the smaller

diameter ground strap terminal over

the stud and retain with a 6-mm

washer and nut. Route the other end

of the ground strap to the threaded

section on the engine and retain with

a SAE washer and M8- 1.25x 16 bolt.

See Figure 15

39.

Slide the supplied intake gasket

over the four studs, then slide the

High-Ram over the studs.

Figure 14. Orientation of the hose clamps on the driver side.

1

/

2

INTAKE HEATER

M6 NUT & M6

WASHERS (2)

M8 X 1.25 BOLT

SAE WASHER

LARGER

DIAMETER

TERMINAL

GROUND STRAP

FACTORY NUTS

Figure 15. High-Ram stud installation.