Pre-season checks, Chapter 11 pre-season checks, Set control switches control power switch – Grain Systems PNEG-1820 User Manual
Page 27: Set control switches, Control power switch
PNEG-1820 CE Compliant Top Dry Series 2000 Autoflow
27
11. Pre-Season Checks
Before the dryer is filled, inspect the unit and check the operation of the dryer as follows. Never enter a
bin where grain is present.
Set Control Switches
•
Moisture Control switch - “ON”
•
Aeration Fan switch - “OFF”
•
Load Auger switch - “OFF”
•
Fan switch - “OFF”
•
Heater switch - “OFF”
•
Dump switch - “AUTO”
•
Dry and Hold switch - “OFF”
•
Autoflow Emergency Stop switch - “OUT”
•
Actuator switch - “ON”
•
Fill System Control Box Emergency Stop switch - “OUT”
Control Power Switch
Turn the control power switch ON. The switch will illuminate. If a fault is found an error message will be
displayed on the screen. If all are found safe, the main drying screen will be displayed.
Figure 11A Top Dry Component Placement