Before the dryer is filled, inspect the unit and check the operation of the dryer as follows. Never enter a
bin where grain is present.

Set Control Switches

Moisture Control switch - “ON”

Aeration Fan switch - “OFF”

Load Auger switch - “OFF”

Fan switch - “OFF”

Heater switch - “OFF”

Dump switch - “AUTO”

Dry and Hold switch - “OFF”

Autoflow Emergency Stop switch - “OUT”

Actuator switch - “ON”

Fill System Control Box Emergency Stop switch - “OUT”

Control Power Switch

Turn the control power switch ON. The switch will illuminate. If a fault is found an error message will be
displayed on the screen. If all are found safe, the main drying screen will be displayed.

Figure 11A Top Dry Component Placement