Chapter 6 installing the wet bin, Raising the load auger, Chapter 6 – Grain Systems PNEG-1891 User Manual
Page 33: Installing the wet bin raising the load auger, Installing the wet bin
Advertising
6
Installing the Wet Bin
Topics Covered in this Chapter
Securing the Dryer Wet Bin Sides
Installing the Belt Guard and Load Motor
Installing the Drive Sheaves and Belts
Installing the Belt Guard Cover
Installing the Grain Intake Hopper
The Parts of the Dryer Wet Bin
Raising the Load Auger
You must raise the load auger before you can install the dryer wet bin.
1. To raise the load auger:
• For dryers eight ft (2.44 m) use the handrails (A)
Figure 6-1 Handrail location for dryers eight ft (2.44 m) in length.
A
Handrails for 8 ft (2.44 m) dryer
• For dryers twelve ft (2.66 m) or longer, turn the turnbuckles on the lift kit (B)
Pneg-1891 Portable Dryers
33