Chapter 6 installing the wet bin, Raising the load auger, Chapter 6 – Grain Systems PNEG-1891 User Manual

Page 33: Installing the wet bin raising the load auger, Installing the wet bin

Advertising
background image

6

Installing the Wet Bin

Topics Covered in this Chapter

Raising the Load Auger

Securing the Dryer Wet Bin Sides

Installing the Belt Guard and Load Motor

Installing the Drive Sheaves and Belts

Installing the Belt Guard Cover

Installing the Grain Intake Hopper

The Parts of the Dryer Wet Bin

Raising the Load Auger

You must raise the load auger before you can install the dryer wet bin.

1. To raise the load auger:

• For dryers eight ft (2.44 m) use the handrails (A)

Figure 6-1 Handrail location for dryers eight ft (2.44 m) in length.

A

Handrails for 8 ft (2.44 m) dryer

• For dryers twelve ft (2.66 m) or longer, turn the turnbuckles on the lift kit (B)

Pneg-1891 Portable Dryers

33

Advertising