19. Hoisting

68

PNEG-805 36' Diameter 40°/45° NCHT Commercial Hopper Tanks

Hoist Instructions (Continued)

Figure 19C

3. It will generally simplify the setting process to bend the sealing lip inward slightly to allow sidewall

sheet clearance. Once tank is in place, bolt the sealing strip to the bottom of the sheet. Shim between
the bottom of the stiffener and the compression angle ring for level alignment if necessary.

4. After tank is secured remove the spider or horizontal bracing and all hoisting attachments

and cables.

Ref #

Description

Ref #

Description

A

2-1/2" Pipe

H

Sidewall Support Angle

B

Bolt Hole

I

Sidewall Sheet

C

2" Pipe

J

Sidewall Stiffener

D

3-1/2" x 1-1/2" Slots (2)

K

Lifting Bracket 3" x 3" x 3/8" Angle

E

Hub Assembly

L

Extra Nut or Sidewall Spacer

F

6" Schedule 40 Pipe

M

3/8" Grade 8 Bolts (4)

G

3" x 3" x 3/8" Angle Iron Welded to Hub (Four (4) Places)