20. Flashing

Flashing Installation

1. Attach flashing to the bin wall using the pre-punched holes at 9-1/3" above the horizontal seam.

2. Attach left side of the first piece of flashing to the sidewall using the connection as shown in

Figure 20A

. Working clockwise, overlap the flashing at the right hand hole of each piece of flashing.

NOTE: If bolts are installed at flashing seam location they will need to be removed.

3. At vertical seams attach flashing that is to span the vertical seams using both left and right holes.

Drill flashing holes from the outside of the bin through the sidewall sheet holes. Remove drilled
flashing and assemble vertical seam bolts and nuts.

(See Figure 20C on Page 71.)

Replace drilled

flashing and attach according to

Figure 20B

. Continue around the bin clockwise.

Figure 20A Flashing Hardware

Hardware Configuration for

Flashing Installation

Figure 20B Vertical Seam Flashing Hardware

Hardware Configuration for Flashing

Installation at Vertical Seams

NOTE: Only difference between normal hardware configuration and vertical seam hardware configuration

is washer.

Ref #

Part #

Description

A

CHT-2104

Flashing

B

S-7569

5/16" Fender Washer

C

S-396

5/16" Nut

D

S-277

5/16" x 1-1/4" Bin Bolt

E

Sidewall Sheet

Ref #

Part #

Description

A

CHT-2104

Flashing

B

S-248

3/8" Washer

C

S-396

5/16" Nut

D

S-277

5/16" x 1-1/4" Bin Bolt

E

Sidewall Sheet