Start-up

Pre.Start-up.Check

Before requesting start-up, check that the installation is
complete and unit is ready. Complete the pre start-up
below (if items are applicable) and the checklist in

Appen-

dix C

for each unit. For torque values on set screws, belt

tension, etc. check under Operation and Maintenance.

1. Check the electrical disconnect is in 1. the ‘Off’ posi-

tion.

2. Check the split section joints are properly installed on

multi-section units.

3. Check that all holes that have been made by the

Installing Contractor after receiving the unit in the
casing, partitions or floor have been well sealed to
prevent air and/or water infiltration.

4. Check the unit for obstructive packaging, objects

near or in fans, dampers, etc.

5. Remove all retaining bolts on fan bases.

a. Check that the fan impellers are rotating freely.
b. Check fan impeller and drive set screws. Tighten

if required.

c. Check the fan bearing set screws or locking col-

lars. Tighten if required.

d. Check fan belt alignment and tension.

6. Check that the air filters are installed and clean.

Replace if necessary. See

Appendix D

for optional

downstream high efficiency HEPA filter installation (if
supplied).

a. Check all face-mounted filters are attached with

four clips each.

b. Check each sliding filter has a retainer at the end

track and well attached blank-offs.

c. Check that the filter pressure differential gauges,

switches or sensors are free of dirt and set at a
value satisfactory to the end user to trigger a fil-
ter change.

7. Check coils if fins have been damaged in shipping,

installation or building construction and are clean.
Straighten fins with fin comb and clean coil if re-
quired.

a. Check all pipe connections are tight and that no

damage has occurred during shipping or instal-
lation.

b. Check that the piping to the coils and WCC have

been completed, piping lines have been flushed,
filled, vented and tested at 1.25 times the oper-
ating pressure.

c. Refer to

Appendix A

for WCC piping installation

and check that it is complete.

8. Scroll compressor RIS vibration isolator bolts are fac-

tory tightened to the correct torque setting for op-
eration and do not require field adjustment.

a. Check that refrigerant components and piping

are in good condition and have no damage or
leaks from shipping or installation.

b. Check that the clearance around the water

cooled condenser (WCC) is in accordance with
minimum recommended clearances.

9. Check motorized damper control arms, control rods

and shafts for tightness.

a. Check that non motorized dampers rotate freely.

10. Check that ductwork is connected, complete and

free of obstructions.

11. Check that condensate drain connections have been

trapped, installed correctly and filled.

12. Check that all shipped loose or field supplied compo-

nents have been correctly installed and wired.

13. Check that the wiring diagram has been marked up

accordingly and left with the unit.

14. Check that all power supplies and control wiring

have been inspected and approved by the Local Au-
thorities having jurisdiction.

15. Check all factory and field wiring connections for

tightness. Tighten if necessary.

16. Check that all fuses are properly installed in holders.
17. Check the voltage at the disconnect switch against

the nameplate and against phase-to-phase readings
on three-phase. If the voltage is not within 10% of
rated or 2% of phase-to-phase, have the condition
corrected before continuing start-up.

18. Check that all field piping and venting installation

and connections for the heating and cooling options
have been completed and tested.

19. Set the heating and cooling enable switches to the

‘Off’ position.