Appendix C: V-Cube™ Start-up Report and Checklist
Venmar CES Inc.
200 Rue Carter
St.-Léonard-d’Aston, QC
Canada J0C 1M0
Email to tech support: [email protected]
Fax: 899-319-2612
Phone: 1-866-4-VENMAR
Unit Identification Information
Project ____________________________________________
Job Name _________________________________________
Job Address _______________________________________
Model Number _____________________________________
Serial Number ______________________________________
Tag ______________________________________________
Jobsite Contact ____________________________________
Email _____________________________________________
Telephone _________________________________________
IMPORTANT
• Complete this form for each unit and email, fax or
mail to Venmar CES immediately after start-up to
validate warranty and to provide valuable informa-
tion for personnel performing future maintenance
or for factory assistance to address below.
• Read the Installation, Operation and Maintenance
Instructions Manual and the EPiC™ System Keypad
Operation Guide and the Sequence of Operation
before proceeding.
• Leave a copy of this report with the owner and at
the unit for future reference and permanent record.
• To ensure proper operation of each unit, qualified
personnel should perform the start-up, complete
the checklist and report.
• All units are functionally tested except when
shipped in multiple pieces. Start-up adjustments
may be required. If the unit is shipped as a single
piece, blowers and compressors (if equipped) are set
up to run correctly when power is connected. If any
blower is running backwards or compressor is mak-
ing loud noises, disconnect power and switch two
leads (on three-phase power) to ensure proper rota-
tion and avoid damage.
• If units are equipped with compressors, power must
be turned on for 24 hours prior to a call for cooling,
for the compressor crankcase heaters to be energiz-
ing to prevent possible damage.
• The Bacview keypad located at the control panel
will allow for manual override for start-up, mode
of operation selection and includes an internal time
clock if remote interlocks are not provided.
Table C1: Pre Start-up Checklist
Checklist Item
Yes
N/A
1
Is the electrical disconnect set to the ‘Off’ position?
2
Have the split section joints been properly installed on multi-sectional units?
3
Have all holes made by the Installing Contractor in the casing, partitions or floor been well sealed
to prevent air and/or water infiltration?
4
Have obstructive packaging, objects near or in fans, dampers, etc. been removed?
a. Has the inside of the unit been cleaned of all debris?
5
Have all retaining bolts on fan bases been removed?
a. Do all the fan impellers rotate freely?
b. Are all fan impellers and drive set screws tight?
c. Are all the fan bearing set screws or locking collars tight?
d. Are all fan belts aligned and have proper tension?
e. Are the fan flexible joint connections well attached?
6
Are all air filters installed and clean?
a. Are all face-mounted filters attached with four clips each?
b. Do all sliding filters have a retainer at the end track and well attached blank-offs?
c. Are the filter pressure differential gauges, switches or sensors free of dirt and set at a value
satisfactory to the end user to trigger a filter change?
VCES-V-CUBE-IOM-1A