Installation preparation, Construct ceiling support continued – GE ZV925SLSS User Manual

Page 11

Advertising
background image

Ceiling

Joist

10-3/4

2x 4 Min.

Cross Framing

Height

Adjustment

Screw Holes

7-1/16"

11

CONSTRUCT CEILING SUPPORT
CONTINUED

Installation Preparation

Ductwork for Installations Vented to the Outdoors
• Use the shortest and straightest duct route possible.

For satisfactory performance, duct run should not
exceed 100 feet equivalent length for any duct
configuration.

• Refer to “Duct Fittings” chart to compute the

maximum permissible length for duct runs to the
outdoors.

• This vent hood must use 8" round rigid duct.
• Install the house ductwork to run horizontally

between ceiling joists or straight up through the
roof.

Finish the Ceiling
• Finish the ceiling surface. Be sure to mark location

of the ceiling joists and cross framing. Check to be
sure the ceiling is level; use shims if necessary.

Ceiling Joint

2x4

10"

Duct

Vent Straight Up

Through The Ceiling

• Secure each 2 x 4 block with at least four (4), #10

wood screws, 3" long (not supplied). Use 8 wood
screws total for the two supports.

The cross framing must be accurately aligned to

assure correct positioning of the hood.

• The cross framing must be level in all directions.

Check with a spirit level and adjust if necessary.

IMPORTANT: The ceiling structure must be capable
of supporting the weight of the hood (approximately
200 pounds) and any inadvertent user contact loads.
The hood support frame will be supported by the
2 x 4 cross framing.

2 x 4 min.

cross framing

Ceiling

joist
7-1/16"

8"

Duct

Ceiling joist

2 x 4

Vent straight up

through the ceiling

10-1/16"

Height

adjustment

screws