4. Commissioning

4−8

Festo P.BE−SPC200−COM−PDP−E N en 0901c

4.1.2 Steps for commissioning the SPC200 as a field bus slave

The following steps are required for commissioning the
SPC200 as a field bus slave:

1. Set the following when configuring the field bus module:

Settings

Description

PROFIBUS address

Permitted address range: 0...125

1)

1)

In some cases is limited by the DP master used

Modification by a DP master is not possible.

2. Install GSD file and symbol file.

3. Configure the PROFIBUS with the appropriate configurĆ

ation software (e.g. with STEP 7 hardware configurator).

4. Test the field bus connection in online mode.

Details can be found in the following sections.