2.

After engine has had sufficient time to warm up, shut engine
off.

3.

Turn SELECT switch to PLATFORM.

4.

From Platform, pull POWER/EMERGENCY STOP switch out,
then push the ENGINE START switch until engine starts.

NOTE:

Footswitch must be in released (up) position before starter will
operate. If starter operates with footswitch in the depressed posi-
tion, DO NOT OPERATE MACHINE.

Shutdown Procedure

IF AN ENGINE MALFUNCTION CAUSES AN UNSCHEDULED SHUTDOWN, DETERMINE THE
CAUSE AND CORRECT IT BEFORE RESTARTING THE ENGINE.

1.

Remove all load and allow engine to operate at low speed
for 3-5 minutes; this allows further reduction of internal
engine temperature.

2.

Push POWER/EMERGENCY STOP switch in.

3.

Turn Platform/Ground Select switch to Off.

Refer to Engine Manufacturer’s manual for detailed information.