SECTION 2 - PROCEDURES

3120765

– JLG Lift –

2-27

mallet, install pivot pin #2 into fly boom assembly
and secure with mounting hardware.

7.

Align the slave leveling cylinder with attach holes in
articulating jib boom pivot weldment. Using a soft
head mallet, install slave leveling cylinder pin #1
into articulating jib boom pivot weldment and secure
with mounting hardware.

2.14 SWING BEARING

Turntable Bearing Mounting Bolt Condition
Check

NOTE: This check is designed to replace the existing bear-

ing bolt torque checks on JLG Lifts in service. This
check must be performed after the first 50 hours of
machine operation and every 600 hours of machine
operation thereafter. If during this check any bolts
are found to be missing or loose, replace missing or
loose bolts with new bolts and torque to the value
specified in the torque chart, after lubricating the bolt
threads with loctite #271. After replacing and
retorquing bolt or bolts recheck all existing bolts for
looseness.

1.

Check the frame to bearing. Attach bolts as follows:

a. Elevate the fully retracted boom to 70 degrees

(full elevation).

b. At the positions indicated on Figure 2-31. try and

insert the .0015" feeler gauge between the bolt
head and hardened washer at the arrow indi-
cated position.

c. Assure that the .0015" feeler gauge will not pen-

etrate under the bolt head to the bolt shank.

d. Swing the turntable 90 degrees, and check

some selected bolts at the new position.

e. Continue rotating the turntable at 90 degrees

intervals until a sampling of bolts have been
checked in all quadrants.

2.

Check the turntable to bearing. Attach bolts as fol-
lows:

a. Elevate the fully retracted boom to 70 degrees

(full elevation).

b. At the positions indicated on Figure 2-30. try and

insert the .0015" feeler gauge between the bolt
head and hardened washer at the arrow indi-
cated position.

c. Lower the boom to horizontal and fully extend

the boom.

d. At the position indicated on Figure 2-30. try and

insert the .0015" feeler gauge between the bolt

head and hardened washer at the arrow indi-
cated position.

Wear Tolerance

1.

With the boom positioned over the side of the
machine, the Upper Boom horizontal with telescope
fully extended and Mid/Lower Boom stowed, (See
Figure 2-31.), using a magnetic base dial indicator,
measure and record the distance between the swing
bearing and turntable. (See Figure 2-32.)

2.

At the same point, with the boom positioned over
the side of the machine, the Upper Boom fully ele-
vated and the Mid/Lower Boom fully elevated, (See
Figure 2-31.) using a magnetic base dial indicator,
measure and record the distance between the swing
bearing and turntable (See Figure 2-32.).

3.

If a difference greater than 0.057 in. (1.40 mm) is
determined, the swing bearing should be replaced.

Figure 2-30. Swing Bearing Feeler Gauge Check

Figure 2-32. Swing Bearing Tolerance Measuring Point