7. Inspect upper lift cylinder attach pin for wear, scor-

ing, tapering and ovality, or other damage. Ensure
pin surfaces are protected prior to installation.
Replace pins as necessary.

8. Inspect inner diameter of boom pivot bushing for

scoring, distortion, wear, or other damage. Replace
bearing as necessary.

9. Inspect all wear pads for excessive wear or other

damage. Replace pads when worn to within 1/8 inch
(3.2 mm) of threaded insert.

10. Inspect extend and retract wire rope attach point

components for cracks, stretching, distortion, or
other damage. Replace components as necessary.

11. Inspect all threaded components for damage such

as stretching, thread deformation, or twisting.
Replace as necessary.

12. Inspect structural units of boom assembly for bend-

ing, cracking, separation of welds, or other damage.
Replace boom sections as necessary.

Assembly

NOTE: When installing fly section wear pads, install same

number and thickness of shims as were removed
during disassembly.

1. Measure inside dimensions of the base and mid

sections to determine the number of shims required
for proper lift.

2. Measure inside dimensions of the mid section to

determine the number of shims required for proper
lift.

3. Install side, top and bottom wear pads to the aft end

of fly section; shim evenly to the measurements of
the inside of mid section.

4. Install retract wire ropes into aft end of fly section,

route wire ropes thru holes in side of fly boom sec-
tion and pull into slot.

5. Install side, top and bottom wear pads to the aft end

of mid section; shim evenly to the measurements of
the inside of mid section.

WHEN ASSEMBLING BOOM SECTIONS, ENSURE THAT THE
BOOM SLIDING TRAJECTORIES HAVE BEEN CLEARED OF
CHAINS, TOOLS, AND OTHER OBSTRUCTIONS.

6. Shim the insides of the boom sections for a total of

1/16 inch (0.062) clearance (if the action is centered,
there will be 1/32 clearance on each side).

7. Slide fly boom section into the mid boom section.

Shim boom, if necessary, for a total of 1/16 inch
(0.062) clearance.

8. Install wear pads into the forward position of the mid

boom section. Shim boom, if necessary, for a total of
2/10 inch (0.20) clearance.

9. Properly position the retraction wire rope sheaves

assemblies at the aft end of the mid boom section;
ensure all sheave-to-mounting block attachment
holes align. Install the sheave pins and secure them
with mounting hardware. Position retract wire ropes
onto the sheaves.

Figure 4-9. Routing Installation of Retract Wire Ropes