SECTION 4 - BOOM & PLATFORM

4-16

– JLG Lift –

3120746

Assembly

NOTE: Lubricate all seals and o-rings with clean hydraulic

oil prior to assembly.

1. Install new seal (7) and bearing (6) on the piston

sleeve (3).

NOTE: Apply a coat of grease to the thrust ring before slid-

ing onto the shaft.

2. Install new seal (8), thrust ring (10) and bearing (9)

on shaft (2).

NOTE: Apply a coat of grease to the thrust ring before slid-

ing onto the end cap.

3. Install new seals (11), back-up ring (12), cap bearing

(13), bearing packing (14) and thrust ring (10) on
end cap (5).

4. Place the actuator in the vertical position, install the

piston sleeve (3) in timed relation to the housing (1).

DO NOT MISALIGN THE SLEEVE TOO MUCH ANY ONE WAY, AS IT
WILL MARK THE CYLINDER BORE.

NOTE: The timing marks (the small punch marks on the

face of each gear), must be aligned for proper shaft
orientation. (See Actuator Timing.)

5. Install the shaft (2) into housing (1) by aligning the

proper punched timing marks. (See Actuator Tim-
ing.)

6. Temporarily tape the threaded portion of the shaft

will help installation past the shaft seals (masking
tape).

7. The end cap (5) is torqued to 40 - 50 ft. lbs. (54 - 68

Nm), such that the actuator begins rotation at
approximately 100 psi (6.895 Bar) pressure.

8. The end cap must be secured against the shaft by

installing axial set screws (4).

Figure 4-21. Actuator Timing