Disassembly

1. Position drive so that one of the fill holes is at the

bottom of the end cover and drain the oil.

2. Remove all bolts holding the motor and Remove

motor from drive.

3. Compress the disc (59) using a simple fixture or

other suitable device.

4. Remove snap ring (66) and release pressure on disc

until loose. Remove tool and disc.

5. Remove the spring (55) from the input shaft (44).

6. Turn unit so that cover (8) is in the up position.

7. Remove the screw plugs (22) and seal rings (21).

8. Remove snap rings (34), and remove the cover unit

(8) from drive.

9. Remove “o” ring (33).

10. Remove the first stage planetary assembly (7).

11. Remove hex bolts (23).

12. Remove ring gear (30) and “o” ring (19).

13. Remove snap rings (15).

14. Pull off planet gears (1) together with cylindrical

roller bearings (11) from spindle (60).

NOTE: Further disassembly of the hub is discouraged. rein-

stallation of the shaft nut (4) requires a special tool
and a torque of 626 ft./ lbs. (876 Nm) for proper reas-
sembly. These components Will Fail if not properly
reassembled.

15. Inspect the planetary stage assemblies as complete

units. Thoroughly clean and check both the gearing
and the bearings for damage and apply new oil. If
the gears or bearings need replacing, they must be
replaced as complete sets.

16. The first stage planetary gears (2)

must be changed

in sets of three pieces.

17. The first stage planetary gears (2)

must be changed

as a complete set of three and JLG recommends
changing the sun gear shaft (43) along with this set
of planets.

18. The second stage planetary bearings (11)

must be

replaced in sets of four pieces.

19. The second stage planetary gears (1)

must be

changed as a complete set of four and JLG recom-
mends changing the sun gear (3) along with this set
of planets.

Disassembly of Cover

1. Loosen and remove hex head bolts (53) to remove

cover (51).

2. Remove shaft rod (56) and “o” ring (54).

3. Remove sleeve (52).

Disassembly of the first stage planetary
assembly (7)

1. Push sun gear shaft (43) out of the first stage.

2. Remove snap rings (14).

3. Press planet pins (5) out of the planet gears (2).

4. Pull cylindrical roller bearing (10) out of the planet

gears (2).

5. Remove snap ring (16) from sun gear (3) and

Remove planet carrier (7) from sun gear (3).

6. Remove thrust washer (49).

Disassembly of second stage planet gears
(1)

Press cylindrical roller bearings out of planet gears (1).

Assembly of first stage planetary assembly
(7)

1. Pre-freeze planet pins (5) and install into planet car-

rier (7).

2. Install planet carrier (7) together with planet pins (5)

on sun gear (3), and install snap ring (16).

3. Pre-heat thrust washer (49) and Install onto sun gear

shaft (43).

4. Put sun gear shaft (43) into sun gear (3).

5. Pre-heat stay rings (17) and install onto planet pins

(5).

6. Pre-heat cylindrical roller bearings (10) and install

onto planet pins (5) and fix bearings with snap rings