Panel installation – Metal Sales Image II Installation User Manual

Page 18

Advertising
background image

© Metal Sales Manufacturing Corporation / Subject to change without notice, effective 6/2011

18

Step 1

Exposed Fastened Panel installation

Installing First Panel

Panel Installation

1. Apply a row of Double Bead Tape Sealant on the top leg of the

Eave flashing.

2. Install first panel so that the panel end has proper overhang

making sure that panel is square to eave and rake. It is critical
that the first panel be straight and square with the building as
it controls alignment of the following roof panels.

3. Fasten panel to substrate with a #8-18 x

3

/

4

" Truss Head Wood-

screw in center of the fastening groove located along the male
leg of the panel. Fastener spacing must be designed to meet
local building codes. It is important that the fastener be placed
in the center of the fastening groove and make sure not to over
tighten screws.

4. Fasten Image II panel with (4) #9-16 x 1" Woodscrews through

Double Bead Tape Sealant, flashing, and into the solid sub-
strate as shown below.

Square panel at Rake (2)

Position panel at Eave (2)

#9-16 x 1

"

Woodscrew (4)

Double Bead Tape Sealant (1)

Truss Head

Woodscrew (3)

CAUTION

Additional screws

may be required for

high snow loading

and steep slopes.

Image II Panel (2)

Double Bead Tape Sealant (1)

#9-16 x 1" Woodscrew (34)

(X) Numbers indicate sequence of installation.