Endwall With Counter Detail

1. Once panels have been installed, field cut the 1" Z-Closure (See

page 33) to fit between the panel ribs.

2. Place a row of Double Bead Tape Sealant across panel

and over each panel rib approximately 2" from panel end.

Before proceeding make sure 1" Z-Closure placement will

accommodate Pitch Break flashing.

3. Install field cut 1" Z-Closure as shown on page 33.

4. Fasten 1" Z-Closure through panel with #8-18 x

3

/

4

" Truss

Head Woodscrews, 4 per panel.

5. Apply a continuous bead of Tube Sealant across top leg of

1" Z-Closure filling any gaps or openings around panel ribs.

Position and install Pitch Break flashing to 1" Z-Closure with

Pop Rivets, 3 per panel.

6. Fasten vertical leg of Pitch Break to the parapet wall with the

appropriate fastener, 1' o.c.

7. Install Counter Flashing, and fasten to parapet wall with

appropriate fastener, 1' o.c. Seal Counter Flashing to parapet

wall with Tube Sealant.

8. If two or more flashings are required, lap the flashing over

the previously installed flashing by a minimum of 2" placing a

bead of Tube Sealant between the flashings and securing with

Pop Rivets 2" o.c.

Optional Endwall

with Foam Closure

(X) Numbers indicate sequence of installation.

Image II Panel (1)

Moisture Barrier

1" Z-Closure (2)

Tube Sealant (10)
Fasteners By Others (8)

Pitch Break (6)

Counter Flashing (9)

Tube Sealant (5)

Pop Rivet, 3 per panel (7)

Double Bead Tape Sealant (4)

Truss Head Woodscrew (3)

Pop Rivet

Double Bead Tape Sealant

Truss Head

Woodscrew