Post installation (testing) – Rockwell Automation 1500 Modular Protection System Conversion Kit (GE Multilin to Bulletin 825 Plus) User Manual

Page 24

Advertising
background image

1500-IN059C-EN-E – June 2013

4-10

Installation

Post Installation (Testing)

Failure to follow these steps can result in damage to

equipment and/or personal injury.

1. Inspect the interior of the enclosure for contamination, loose bolts,

tools or metal chips, and vacuuming the enclosure is recommended.

2. Account for all the tools used. If a tool or hardware is unaccounted for,

do not energize the equipment.

3. Inspect the wiring and the control scheme to ensure proper operation.

Extra care should be taken when inspecting the connections for the cur-

rent transformer and ground fault circuits, to ensure neither circuits are

open or short-circuited during power-up.

4. For medium voltage controllers, follow items 5 though 7. For other

styles of controllers, the intent of this section is to apply control voltage

to the controller circuit, including the 825 Plus.

5. The medium voltage non-load break isolation switch must be in the

fully opened position (the isolation switch handle moved to the OFF/

down position).

6. Connect a remote 120VAC external power source to the ‘NORMAL-

OFF-TEST’ (N-O-T) switch assembly test receptacle located in the low

voltage compartment. (Figures 4.28 and 4.29)

7. Turn the N-O-T selector switch to the TEST position. (Figure 4.29)

With the selector switch in the test position, power will

be applied to the control circuit. Additional caution must

be taken to prevent accidental contact with the 120VAC.

Figure 4.8

Figure 4.9

ATTENTION

IMPORTANT